Project

SOCAR Ammonia and Urea Complex

Civil construction and building works including HVAC systems; structural steel works; piping prefabrication and erection, including painting and insulation; equipment installation; and electrical and instrumentation works for the plant. The plant is designed to produce 1,200 MT of ammonia and 2,000 MT of urea per day.

Volume of works

Excavation218,915.00 m3
Backfilling146,548.00 m3
Rebarapprox. 6,000.00 Ton
Concreteapprox. 65,000.00 m3
Road & Pavement (Asphalt)43,299.00 m2
Road & Pavement (Concrete)4,960.00 m3
BUILDINGS (5 ea)6587 m2
Structural Steel Erection5,958.00 Ton
Piping Works348,873.00 DI
Equipment Erection Works10,631.00 Ton
E & I Cable Pulling Works1,078.00 km
Painting Works125,753.00 m2
Insulation Works58,353.00 m2