SOCAR HAOR Tank Erection | Package A

Installation, insulation, painting, and hydrotesting services for six process tanks (480 tons) under Package A of the SOCAR HAOR Modernization and Reconstruction Project.

Volume of works

Item No.DescriptionApplied CodeTank TypeI.D (m)H (m)
141-T-401AMINE STORAGE TANKAPI 650CRT2.44.88
241-T-501SULPHUR TANKAPI 650CRT6.17.13
344-T-001ASour Water Equalization TankAPI 650CRT1617.1
444-T-001BSour Water Equalization TankAPI 650CRT1617.1
556-T-001Slop TankAPI 650CRT6.37
656-T-401Methanol Storage TankAPI 650CRT1211