AZERKIMYA Steam To Power
Client: SOCAR Uniper
Location: Sumgayit, Azerbaijan
Start date: July 2019
Scope of work: Construction works of switchgear building, steam turbine building and air-cooled condensed building, equipment and pipeline installation works around buildings and landscaping works in the unit.
Disciplines: Civil, piping, structural steel, painting/insulation, equipment erection, electrical and instrumentation.
Volume of works:
Excavation | 320m3 |
Backfilling | 550m3 |
Concrete | 1,600m3 |
Structural Steel Erection | 600Ton |
Piping Works | 15,000WDI |
Equipment Erection Works | 451Ton |
E & I Cable Pulling Works | 378km |
AZERKIMYA Steam To Power